Posted - 08/01/2000 : 8:07:00 PM hi, I have problems with linking the y axes in two layers. the lower limit: Y1=f(Y1) is updating the starting point OK. But the upper limit (Y2=f(Y2)) seems not to have ANY effect, no matter if I write Y2=2*Y2 or Y=1000+Y2, or anything else. ? any idea? thanks
stefan
1 L A T E S T R E P L I E S (Newest First)
Barb Tobias
Posted - 08/01/2000 : 8:55:00 PM This problem was fixed in Patch 2 for Origin 5.0.